Riverwalk Logo
Pottery Shards

Preston Redevelopment Agency

Town Offices  389 Route 2  Preston CT 06365

CSS3 Dock Menu Css3Menu.com

Remediation & Demolition

Bick Pile

Brick piles waiting to be palletized - 6/26/2012

As of June, 2012, twenty (20) of the site's 55 buildings have been abated and razed.  Progress in remediation and demolition is proceeding with State and Federal EPA funding (grants), Town matching funds, and sale of recoverable scrap materials. 

Building demolition

Demolition work on site

As each building is removed, and environmental concerns dealt with, the site's potential becomes more evident.

Former Powerhouse site

Foreground - former powerhouse location

The former administration building has been assessed as being structurally sound and identified for adaptive reuse. It has been weatherized.

Administartion Building

We will post news of new demolitions as such occur.