Remediation & Demolition

Brick piles waiting to be palletized - 6/26/2012
As of June, 2012, twenty (20) of the site's 55 buildings have been abated and razed. Progress in remediation and demolition is proceeding with State and Federal EPA funding (grants), Town matching funds, and sale of recoverable scrap materials.

Demolition work on site
As each building is removed, and environmental concerns dealt with, the site's potential becomes more evident.

Foreground - former powerhouse location
The former administration building has been assessed as being structurally sound and identified for adaptive reuse. It has been weatherized.

We will post news of new demolitions as such occur.